Dowling-Fulton 345-kV Transmission Line Tap to Melbourne Substation Project
The Dowling-Fulton 345 kV Transmission Line Tap to Melbourne Substation Project proposes to build a new, approximately 9 miles long, 345-kV transmission line that will extend from the existing Dowling-Fulton 345-kV Transmission Line to the proposed Melbourne Substation. The transmission line will be supported primarily on steel monopole structures. ATSI will also construct two approximately 0.5 mile long 345-kV transmission lines to connect the existing Sydney Substation to the proposed Melbourne Substation. The transmission line will be supported primarily on steel monopole structures.
The project will be located in the communities of the Delta Village, Fulton, Pike, Swan Creek and York Townships, Fulton County, Ohio. The Project will to enhance electric service reliability for existing customers, add redundancy to the network, and allow for future growth.
Project Documents
- Fact Sheet
- Application filed with the Ohio Power Siting Board
- Cultural Report (redacted) filed with the Ohio Power Siting Board
A paper copy of the application can be supplied within five business days upon request at no more than the cost of printing and shipping. A paper copy can be requested by contacting the transmission project hotline at 1‐888‐311‐4737 or by email (transmissionprojects@firstenergycorp.com). The project name and case number (22-0248-EL-BTX) should be referenced in all communications.
Local Public Hearing
A local public (non-adjudicatory) hearing will be held Wednesday, December 6, 2023, at 6 p.m. at the below location. At this meeting, the Board shall accept written and oral testimony from the public.
Delta American Legion Post A.E.E.E.W. No.373
5939 SR 109
Delta, Ohio 43515
Evidentiary Hearing
An evidentiary (adjudicatory) hearing will be held Tuesday, January 9, 2024, at 10 a.m. at the below location.
Public Utilities Commission of Ohio
Hearing Room 11-C
180 East Broad Street
Columbus, OH 43215-3793
Public Information Meeting
The purpose of public informational meeting is to explain the proposed project and to seek input from the community.
- Wednesday December 7, 2022
6 p.m. to 8 p.m.
American Legion Building
5939 State Route 109
Delta, OH 43515
A virtual public information meeting for those that cannot attend can be viewed at: https://firstenergy.consultation.ai/melbourne/